Haddricks Mill roundabout improvements to start

Work is to start shortly to improve Haddricks Mill roundabouts in South Gosforth.

The improvements are part of Newcastle City Council’s plans to improve key junctions across the city from the Blue House Roundabout, Jesmond Dene Road to Haddricks Mill and beyond.

You can read more about the previous plans from August 2016 for the Blue House Roadabout and Jesmond Dene Road elsewhere on this website.

The upcoming Hadricks Mill improvements were also opened for public consultation in August 2016, although the work that is now to take place is much less than the original plan to widen the Haddricks Mill junction and replace the existing 2 roundabouts with 1 substantially larger roundabout.

You can read more about what Newcastle City Council plan below.

The following announcement has been made by Newcastle City Council:

Haddricks Mill double roundabout in South Gosforth is set to benefit from £4m investment to improve safety and congestion through an upgrade of the ageing infrastructure in the area.

A well-known collision hotspot Haddricks Mill also suffers from congestion, delays and safety issues – particularly in relation to cyclists.

Six roads converge

Six roads converge onto the junction which is used by tens of thousands of commuters each day, with queues building up at peak periods, leading to longer journey times and affecting air quality in the area.

The major investment will renovate the bridge the junction sits on, realign traffic lanes to improve lane discipline, re-position the mini-roundabouts to increase capacity and install new crossing facilities that will help balance traffic flow in peak periods.

This should have the added benefit of reducing high levels of congestion and improving air quality.

Cllr Arlene Ainsley, cabinet member for transport and air quality said: “Haddricks Mill is a notorious junction and I am pleased it is to be given a much-needed overhaul.

“This is a major safety and infrastructure upgrade scheme, designed to improve safety and smooth traffic flow at peak periods – reducing congestion and encouraging more sustainable choices of travel – which should improve air quality.

“Due to the junction’s location over the Ouseburn and several businesses lining the approaches, the options available to improve it are limited but we have designed a scheme that delivers safety and congestion improvements for one of the key routes into the city and which takes into account residents’ feedback from our earlier consultation.”

The works are a scaled-down version of the proposals the council consulted on in 2016 and addresses many of the concerns raised by residents such as the size of the junction, changes to access to a local housing estate and proposed banned turns and movements.

Work will last until 2020

The council plans to take advantage of the current closure on Killingworth Road to start preparatory work on the junction, reducing the disruption to commuters before the main works start.

The main programme of work to the carriageway will be begin this spring and should last until early 2020.

However, the council is committed to minimising disruption and keeping two-way traffic on all approaches – apart from occasional night-time and weekend closures for resurfacing towards the end of the programme.

Minor tree removal is necessary with up to ten trees needing to be removed as part of the scheme, but the council will replace them with at least 30 trees to further improve the environment.

The full package of improvements includes:

•           Water-proofing and maintenance to the bridge the junction sits on

•           Re-construction of carriageway

•           Raised bridge parapets to improve safety

•           Realignment of the roundabouts to increase capacity

•           Widened lanes and better signage to improve lane discipline

•           Improved crossing points for pedestrians and cyclists on the main arms of the junction to control the flow of traffic at peak periods

•           Improved cycling and walking facilities including accessible routes to the Wagon Way

•           Segregated cycle lanes incorporated where space allows

•           Raised table to reduce speeding on Hunters Road

Full plans for Haddricks Mill junction

You can also download the full plans for Haddricks Mill junction.

And read more in a leaflet produced by Newcastle City Council.

Planned Newcastle Northern Access Corridor road

The works to Haddricks Mill is part of planned improvements for a key transport corridor which runs from Cowgate to the north of the city, including Blue House roundabout, Haddricks Mill and Killingworth Road.

Revised Blue House Roundabout plans

Final designs for Blue House are being developed and modelled based on recommendations from a working group set up following the backlash to original proposals in the summer of 2016.

These will be publicised this summer.

Killingworth Road ongoing works

We’re investing over £13.5m to widen the well-known pinch point at Killingworth Road.

This funding is focused on addressing some major maintenance issues including the retaining wall and ensuring the bridge over the Ouse that the Haddricks Mill junction sits on is safe for future generations.

Over-runs to the gas diversion works has meant a delay to the re-opening of Killingworth Road. Newcastle City Council would like to thank everyone for their patience during the roadworks. You can read more here.

The project received £4m from the Government’s Local Growth Deal through the North East Local Enterprise Partnership (LEP). The Local Growth Deal is supporting major capital investments to promote innovation, economic and skills infrastructure and sustainable transport as part of the North East Growth Deal.

The above news story was issued by Newcastle City Council and included on the Newcastle City Council website. It has been included here for information and does not necessarily represent the views of High West Jesmond Residents’ Association. 

Killingworth Road could re-open from May

The following announcement has been made by Newcastle City Council:

Newcastle City Council is advising motorists that Killingworth Road could re-open to traffic from May providing the weather conditions remain stable.

The council say current project timelines, barring severe weather events such as last year’s Beast from the East, could see the road partially open to traffic before summer.

Due to on-going construction works, initially only one-way (south bound) traffic and pedestrians could be accommodated in the available road space. Estimates show two-way traffic could use the road from July onwards.

Essential work by contractors is still taking place around the Metro bridge which has pushed back the early 2019 re-opening. Further construction work is required before the road can safely be re-opened to traffic and pedestrians.

Project manager, Jon Higgins from Newcastle City Council said: “We appreciate the inconvenience the extended closure on Killingworth Road has had on the travelling public and we would like to reassure motorists that we are working closely with contractors to open the road as soon as possible.

“Current estimates show that we could have one-way traffic using the road in May, but this is heavily based on no further complications such as severe weather conditions further hampering progress on site.

“We know this is disappointing for motorists and we appreciate their patience during the extended road closure, but safety is paramount before we can allow traffic and pedestrians back on Killingworth Road.”

The project was beset with difficulties during the gas pipes replacement programme with Northern Gas Networks which caused it to severely over-run.

Engineers have been reviewing the timeline to compensate for the delays but with multiple contractors involved and complex engineering work required the project has slipped back.

Contractors are currently finalising piling works to construct new retaining walls next to the Metro bridge. Once this is complete, construction teams can access the site under the bridge to do final road-widening works.

A phased opening is planned which will allow traffic and pedestrians with safe routes through the roadworks. As the scheme progresses, further road space will become available and two-way traffic will be introduced.

The council will continue the last stages of the works with installing widened footpaths, cycle lane, bus lane, vehicle lane and safer crossings.

Construction work will continue into early 2020.

Once complete, the project will improve air quality, reduce journey times and improve public transport reliability on one of the major commuter routes into the city.

The above news story was issued by Newcastle City Council and included on the Newcastle City Council website. It has been included here for information and does not necessarily represent the views of High West Jesmond Residents’ Association. 

MP writes to Northern Gas Networks over extended closure of Killingworth Road

Catherine McKinnell, MP for Newcastle upon Tyne North has written a letter to Northern Gas Networks about the ongoing closure of Killingworth Road and the disruption caused to local residents and businsses.

The letter was addressed to Mark Horsley, the Chief Executive Officer of Northern Gas Networks.

Northern Gas Networks is responsible for the delivery of gas to 2.7 million homes and businesses in the North East, Northern Cumbria and much of Yorkshire.

Residents can read the letter which was published on Catherine McKinnell’s Twitter page twitter.com/CatMcKinnell    @CatMcKinnell

Holding reply from Northern Gas Networks

A response was made on Twitter by Northern Gas Networks  @NGNgas where they said: “We’ve seen your letter and we’ll have a direct response to you very soon.”

Killingworth Road extended closure until 2019

The work on Killingworth Road was originally planend to be completed in February 2018 but there was then a delay until June 2018.

It was then announced that Killingworth Road (the A189), an important business and commuter route, would continued to be closed until 2019 due to ongoing delays with the work.

You can read the MP’s letter below.

 

 

Annual Ward Priority Setting meeting

Residents are invited to attend a meeting with Dene & South Gosforth Ward councillors to help determine the priorities for the ward for the year ahead.

The meeting will take place on Tuesday 24 July 2018, 7pm at Trinity Christian Community Centre, Lartington Gardens, Newcastle upon Tyne, NE3 1SX.

The meeting is scheduled to finish at 8.30pm.

Trinity Christian Community Centre, Lartington Gardens, Gosforth

Topics for discussion

According to the agenda for the meeting (available on the Dene & South Gosforth Ward Committee meetings page of Newcastle City Council’s website), the meeting will feature:

  • an update from Northumbria Police – from A/Sgt 918 Wilson
  • an update from Graham Grant, Newcastle City Council on Transport Schemes including
  • Killingworth Road, Haddricks Mill roundabouts and Blue House roundabout
  • an update on community groups and community action across Dene & South Gosforth Ward (this will include both our local community groups – the High West Jesmond Residents’ Association and the Friends of the Valley and Little Dene – FOVALD)
  • ward finance including grant applications
  • agreement of priorities and action of Dene and South Gosforth Ward 2018/19

According to papers on Newcastle City Council’s website, Dene & South Gosforth ward has been allocated £3,565 to spend (amount is before decisions on grants currently under consideration).

Share your view with Council survey

The council has also set up a survey and invited residents to complete this – you can find this survey on the council-run Let’s talk Newcastle website on the Dene and South Gosforth Annual Ward Priorities Meeting page.

The following information has been issued by Newcastle City Council:

Membership of Dene and South Gosforth Ward Committee

Councillor Wendy Taylor, Councillor Karen Robinson and Councillor Henry
Gallagher

Watch the short YouTube video to find out more:

General Information on Ward Annual Priority Setting meetings

Each of the 26 Wards of the city will hold 1 annual targeted event to identify
ward priorities.

Annual events will be led by Ward Councillors in consultation with local
residents and stakeholders to share identified draft priorities and seek
validation and commitment for collaborative solutions with partners and the
community and voluntary sector.

Ward priorities will be agreed for the following 12 months and will inform
ward committee budget expenditure.

Annual events will focus on priorities for the ward and what we can do in
partnership, encouraging all stakeholders to be part of the response

Identified ward priorities will inform a work programme / action plan for the
ward and we will work directly with communities based on core themes of
active citizenship, building community capacity, behavioural change and
developing community partnerships.

Common themes will be considered where joint action plans can be
developed to avoid duplication and promote best practice.

Agenda for meeting

A copy of this agenda is available on the Newcastle City Council website on the Dene & South Gosforth Ward Committee meetings page.

Further information can be obtained from the Communities Officer:

Louise Cameron Tel:0191 277 1786 Email: louise.cameron@newcastle.gov.uk

The above ward committee meeting details was issued by Newcastle City Council and included on the Newcastle City Council website. It has been included here for information and does not necessarily represent the views of High West Jesmond Residents’ Association. 

 

Railings in High West Jesmond

Have you ever thought about the railings around the sreeets of High West Jesmond?

A heritage post by Chris Morgan

Recently the subject of the original iron railings came up.

A few samples have survived, almost all on corners, which leaves one to suspect this was policy.

I’d previously spotted sections that could have been deep in a privet hedge, but most of these samples pictured here couldn’t have been hidden in a hedge.

Several houses have added their own replacements and one near the bottom of Treherne Road gets very close to the original.

How many more sections have survived?

Walk the bounds – a tour of High West Jesmond

Find out more about the fascinating history of High West Jesmond and join us for a guided walk with Chris Morgan on Sunday 3 June 2018.

Find out more on our Walk the Bounds page.

Blue House recommendations slide deck available

Current view of Blue House Roundabout, High West Jesmond – from Google Maps

The Blue House Working Group recently made recommendations to Newcastle City Council about the Blue House Roundabout and a public meeting was arranged on 12 March 2018 so that local residents could hear more from the working group.

Download the BHWG presentation

The full 52 page pdf slide deck used for the 12 March 2018 presentation has now become available and has been placed on the Blue House Working Group website here – Blue House Working Group 12 March 2018 presentation

Read more about the 12 March 2018 in our short article on this website Meeting hears recommendations from Blue House Working Group